Southern Pacific 9010

The Trucks, Page 2
-- August 17, 2015 --
After the connections were made to the intermediate gear box and cooling lines, CJ filled the system with the proper gear oil.  It was a pleasure to see the oil level come up in the glass and to find that there were no leaks.  Meanwhile, Rich continues needle gunning and cleaning the frame.  This side seemed to be especially oily and dirty.


Shortly after congratulating ourselves on a job well done, we were checking some truck height dimensions and discovered that our new truck was sitting too high, even without the locomotive weight on it.   This issue was traced down to a modification made either by Plasser when the RM63 was built or Colas Rail when the trucks were rebuilt.  Someone had welded 15mm thick pads on the bottom of all of the equalizer levers.  If the truck were to be installed right now, the locomotive would exceed the federal rule regarding height at the rear end.  I made the decision that the pads would have to be removed to put the equalizers back to their stock condition.  The only way to get access to them was to raise the equalizer ends out of the bearing carriers.   To do this, we had to remove all 3 cardan shafts, remove the brake stabilizer rods, disconnect the torque end of each gear box from its cross member,  and remove the pedestal binders.  Gerry and Dick dove right in with help on these jobs.

With jacks and blocking, the frame and equalizers were raised until they were high enough to enable working on the inner set of bar ends.  A 1/16 inch cutting wheel was used to cut through the welds on the ends and down the outside.  Then, the pad was forced down in order to break the weld on the other side of the pad.  The sides of the bars were ground so they had a angled contour and the bottoms were ground to have the slight radius.


The first photo clearly shows an added pad while the second is an illustration of what the end of the equalizer should look like.  Removing the pads from the outside equalizers was not difficult but the inside equalizers were a challenge.

-- September 04, 2015 --
While the truck was jacked up in the air, I decided to attach the newly made sander nozzle brackets.  These were removed by Plasser when the ballast cleaning machine was built.  The brackets are also missing from the front truck but these were removed by the SP during the camera car conversion.  I am installing only the brackets on the rear truck for now.  We had no useful drawings for the brackets so they were scaled from photographs (by our ace photo-scaler Bob Zenk) onto cardboard and compared against photos.  They turned out quite nicely.  The sand nozzles and clamping brackets will come later.  We then re-installed the three Cardan shafts and torqued the flange bolts to 450 foot pounds using a 4-foot torque wrench and a custom made wrench extender.  Finally, Gerry filled the gear boxes with fresh hypoid gear oil.


-- October 15, 2015 --
The next items on the work list were the 2 safety straps around the rear cardan shaft.  These were not original to the truck as built by Krauss Maffei but were a Southern Pacific modification designed to protect the transmission from damage in the event a cardan shaft universal joint should break.  Once again, there were no plans, just a photo taken of one of the trucks that was set aside to be sent to Plasser.  Oddly, neither of the trucks we purchased from France showed any signs of the straps.  We suspect that the straps were applied whenever a truck was removed from a locomotive and fortunately, both trucks under the 9010 had the modification so we were able to get some basic dimensions for the main strap.  

Our rear strap is a bit unlike the original design due to the differences between the Maybach and Voith gear boxes.  We resorted to making a cardboard template because of all the odd angles and curves involved.  The template was taken to our friends at Melrose Metals and they used it to program their CNC machine.

Once the rear strap was bolted into place, I made the small curved plate that would prevent the shaft from falling onto the gear box.

We also installed the flange lubricators that Dick had cleaned and set aside.  These are original to the trucks.

-- October 21, 2015 --
Finally, the truck is fully checked, repaired, lubricated, un-modified and painted.

-- May 16, 2016 --
The big day finally arrived.  May 12, 2016 is the day on which the 9010 received her rebuilt rear truck.  It all started 2 days before when Rich and Gerry switched out the entire west end of the yard to prepare space for the work and the pair of 275 ton cranes from Peninsula Cane.  The rebuilt truck and the spare truck exchanged places with the new truck being left outside under cover until Thursday the 12th.

Because of the way in which the locomotive body connects to the trucks, it is necessary to lift the locomotive straight up to a height of about 7 feet.  The height is required to clear the intermediate gear box on the new rear truck.  The first thing we did was weigh the new truck so we would have a record of it (43,000#).  The old rear truck was then pullled west where a crew headed by Bill and Denny took care of the sliding plates and springs while the front truck was pulled east into the shop where another crew took care of the spring work.  The reason for the spring work was covered in update:  Mechanical Work  





Return To Main Page